Project Information

Installation and maintenance of Monolithic Refractory on Boiler 2x110MW Unit 1 at PLTU Sebalang, Tarahan, Katibung District, South Lampung Regency, Lampung.

PT PLN (Persero)

Katibung District, South Lampung

Monolithic Refractory Installation

PLTU Sebalang

Project Period

This Monolithic Refractory Installation project was carried out periodically in the following timeframes:

PLTU Sebalang Project - Hafila Daya Utama
PLTU Sebalang Project - Hafila Daya Utama PLTU Sebalang Project - Hafila Daya Utama
2017
Boiler 110MW Unit 1
01 – 05 March 2017
14 – 23 May 2017
25 Sept – 03 Oct 2017
22 Nov – 01 December 2017
Boiler 110MW Unit 2
16 – 29 July 2017
2018
Boiler 110MW Unit 1
28 April – 09 May 2018
Boiler 110MW Unit 2
03 – 07 January 2018
March 2018
23 June – 02 July 2018
2019
Boiler 110MW Unit 1
18 – 25 January 2019
23 – 30 June 2019
Boiler 110MW Unit 2
02 – 10 February 2019
02 Sept – 01 Nov 2019
2020
Boiler 110MW Unit 1
17 March – 29 June 2020