Project Information

Installation and maintenance of Monolithic Refractory on 100 MW Boiler Unit 3 and 100 MW Boiler Unit 4 at PLTU Tarahan, Jl. Lintas Timur Sumatera No. Km. 15, Rangai Tri Tunggal, Katibung District, South Lampung Regency.

PT PLN (Persero)

Katibung District, South Lampung

Monolithic Refractory Installation


PLTU Tarahan

Project Period

This Monolithic Refractory Installation project was carried out periodically during the following periods:

Brick lining Indonesia, brick lining company, refractory Indonesia, Hafila Daya Utama, refractory company in Indonesia, refractory services Indonesia, refractory projects Indonesia
Brick lining Indonesia, brick lining company, refractory Indonesia, Hafila Daya Utama, refractory company in Indonesia, refractory services Indonesia, refractory projects Indonesia Brick lining Indonesia, brick lining company, refractory Indonesia, Hafila Daya Utama, refractory company in Indonesia, refractory services Indonesia, refractory projects Indonesia
2013
100 MW Boiler Unit 4
20 – 26 January 2013
1 December 2013 – 4 January 2014
100 MW Boiler Unit 3
10 – 17 March 2013
2014
100 MW Boiler Unit 4
23 – 28 February 2014
3 – 8 June 2014
100 MW Boiler Unit 3
1 March – 3 April 2014
2015
100 MW Boiler Unit 4
19 Jan – 05 Feb 2015
29 Mar – 04 Apr 2015
24 – 31 May 2015
11 – 14 July 2015
100 MW Boiler Unit 3
10 – 21 June 2015
2016
100 MW Boiler Unit 4
13 Jan – 5 Feb 2016
26 – 28 December 2016
100 MW Boiler Unit 3
2 – 14 March 2016
14 – 21 November 2016
2017
100 MW Boiler Unit 3
14 – 23 January 2017
5 August – 11 October 2017
2018
100 MW Boiler Unit 4
20 Jan – 21 Mar 2018
26 Oct – 9 Nov 2018
100 MW Boiler Unit 3
6 August – 28 Oct 2018
2019
100 MW Boiler Unit 4
5 March – 21 July 2019
100 MW Boiler Unit 3
20 – 25 August 2019
2020
100 MW Boiler Unit 4
12 – 20 January 2020
100 MW Boiler Unit 3
3 – 15 February 2020