Project Information

Installation and maintenance of Monolithic Refractory on Boiler 2x16.5 MW Unit 2 at PLTU Bolok, Kuanheum, West Kupang, East Nusa Tenggara.

PT PLN (Persero)

West Kupang, East Nusa Tenggara

Monolithic Refractory Installation

PLTU Bolok

Project Period

This project was carried out during the following period:

Monolithic refractory project PLTU Bolok, PT Hafila Daya Utama, refractory installation Indonesia
Refractory installation at PLTU Bolok by PT Hafila Daya Utama Refractory project PLTU Bolok, Indonesia
2018
Boiler 2x16.5 MW Unit 2
April 28 – May 19, 2018