1 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Jan 20 - 26,2013 |
2013 |
2 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 10 - 17, 2013 |
2013 |
3 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 10 - 17, 2013 |
2013 |
4 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Feb 23 - 28, 2014 |
2014 |
5 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 1 - April 3, 2014 |
2014 |
6 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
June 3 - 8, 2014 |
2014 |
7 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Jan 19 – Feb 05, 2015 |
2015 |
8 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 29 – Aprl 04, 2015 |
2015 |
9 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Instalasi Refractory Monolithic |
PLTU Tarahan |
May 24 – 31, 2015 |
2015 |
10 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
June 10- 21, 2015 |
2015 |
11 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
July 11 – 14, 2015 |
2015 |
12 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Jan 13 – Feb 5, 2016 |
2016 |
13 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 2 - 14, 2016 |
2016 |
14 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Nov 14 - 21, 2016 |
2016 |
15 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Dec 26 – 28, 2016 |
2016 |
16 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Jan 14 – 23, 2017 |
2017 |
17 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
August 05 – Oct 11, 2017 |
2017 |
18 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Jan 20 – Macrh 21, 2018 |
2018 |
19 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
August 6 – Oct 28, 2018 |
2018 |
20 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
Oct 26 – Nov 9, 2018 |
2018 |
21 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
March 5 – Jul 21, 2019 |
2019 |
22 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
20 agustus – 25 Agustus 2019 |
2019 |
23 |
Re-install Refractory of Boiler 100 MW Unit 4 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
12-20 Januari 2020 |
2020 |
24 |
Re-install Refractory of Boiler 100 MW Unit 3 PLTU Tarahan |
Refractory Monolithic Installation |
PLTU Tarahan |
3-15 Februari 2020 |
2020 |
25 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
26 – 30 November 2016 |
2016 |
26 |
Re-Install Refractory of Boiler 112Mw unit 1 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
30 Nov – 2 Desember 2016 |
2016 |
27 |
Re-Install Refractory of Boiler 112Mw unit 1 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
27 April – 10 Mei 2017 |
2017 |
28 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
27 Mei – 01 Juni 2017/td>
| 2017 |
29 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
November 2017 |
2017 |
30 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
Maret 2018 |
2018 |
31 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
April - Juni 2018 |
2018 |
32 |
Re-Install Refractory of Boiler 112Mw unit 2 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
16 Desember 2018- 18Januari 2019 |
2018 |
33 |
Re-Install Refractory of Boiler 112Mw unit 1 PLTU Teluk Sirih |
Refractory Monolithic Installation |
PLTU Teluk Sirih |
July-Agustus 2019 |
2019 |
34 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
01 – 05 Maret 2017 |
2017 |
35 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
14 Mei – 23 Mei 2017 |
2017 |
36 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
16 Juli – 29 Juli 2017 |
2017 |
37 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
25 Sept – 03 Okt 2017 |
2017 |
38 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
22 Nov – 01 Desember 2017 |
2017 |
39 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
3 Januari – 7 Januari 2018 |
2018 |
40 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
28 April - 9 Mei 2018 |
2018 |
41 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
Maret 2018 |
2018 |
42 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
23 Juni - 2 Juli 2018 |
2018 |
43 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
18 Januari - 25 januari 2019 |
2019 |
44 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
2 Februari -10 februari 2019 |
2019 |
45 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
23 Juni - 30 Juni 2019 |
2019 |
46 |
Re-Install Refractory of Boiler 110Mw unit 2 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
2 September - 1 November 2019 |
2019 |
47 |
Re-Install Refractory of Boiler 110Mw unit 1 PLTU Sebalang |
Refractory Monolithic Installation |
PLTU Sebalang |
17 Maret - 29 Juni 2020 |
2020 |
48 |
Re-Install Refractory of Boiler 2x60Mw unit 1 PLTU Pulang Pisau |
Refractory Monolithic Installation |
PLTU Pulang Pisau |
2-10 Februar 2019 |
2019 |
49 |
Re-Install Refractory of Boiler 2x60Mw unit 2 PLTU Pulang Pisau |
Refractory Monolithic Installation |
PLTU Pulang Pisau |
18-25 Maret 2019 |
2019 |
50 |
Re-Install Refractory of Boiler 2x10Mw unit 1 PLTU Ketapang |
Refractory Monolithic Installation |
PLTU Ketapang |
7-16 Oktober 2019 |
2019 |
51 |
Re-Install Refractory of Boiler 2x10Mw unit 2 PLTU Ketapang |
Refractory Monolithic Installation |
PLTU Ketapang |
8-23 November 2019 |
2019 |
52 |
Re-Install Refractory of Boiler Stocker 2x7Mw unit 1 PLTU Sanggau |
Refractory Monolithic Installation |
PLTU Sanggau |
12-23 Juli 2020 |
2020 |
53 |
Dismantling & Installation Refractory Brick in Vertical Kiln Double Shaft (Cimprogetti) 450 Tpd |
Refractory Brick Installation |
PT. RAPP Riau |
11 Mei-14 juli 2015 |
2015 |
54 |
Refractory installation of Brick Kiln Tonasa V |
Refractory Brick Installation |
PT. Semen Tonasa |
28 Mei-26 juli 2013 |
2013 |
55 |
Insulation & Scaffolding Install vertical lime Kiln [Filter Dust Collector] |
Instalasi Isolasi Thermal Jaketing & Scaffolding |
PT. Batumas Mekar Agung |
May 28 - July 26, 2013 |
2013 |
56 |
Insulation & Scaffolding Install vertical lime Kiln [Filter Dust Collector] |
Instalasi Isolasi Thermal Jaketing |
PT. Batumas Mekar Agung |
Oct 8 - 13, 2014 |
2014 |
57 |
Insulation Thermal Ducting Pipe Stack & Fabrication Ventilator Ducting |
Instalasi Isolasi Thermal Jaketing |
PT. Batumas Mekar Agung |
November 2014 |
2014 |
58 |
Recondition Refractory in Vertical Lime Kiln - Double Shaft (Cimprogetti) 150 Tpd |
Refractory Brick Installation |
PT. Batumas Mekar Agung |
July 4 – 5, 2016 |
2016 |
59 |
Recondition Refractory in Vertical Lime Kiln - Double Shaft (Cimprogetti) 150 Tpd |
Refractory Brick Installation |
PT. Batumas Mekar Agung |
July 03 - 10, 2017 |
2017 |
60 |
Installation of Refractory Boiler 2x135 MW |
Refractory Monolithic Installation |
PT. Cikarang Listrindo |
July 03 - 10, 2017 |
2017 |
61 |
Installation Refractory Brick in Vertical Lime Kiln Single & Double Shaft (MAERZ) 200 Tpd at New Greenfield Calcination Project |
Refractory Brick Installation |
PT. Bhumiadya Indonesia |
April 09 2016 – May 20, 2017 |
2017 |
62 |
Installation Brick at Hot Gas Generator - Padalarang |
Refractory Brick Installation |
PT. Bhumiadya Indonesia |
June 27 – July 1, 2016 |
2016 |
63 |
Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari |
Refractory Monolithic Installation |
PLTU Banjarsari |
Nov 4 - Dec 31, 2016 |
2016 |
64 |
Refractory Installation Boiler 135 Mw unit 1 PLTU Banjarsari |
Refractory Monolithic Installation |
PLTU Banjarsari |
May 30 -June 26, 2017 |
2017 |
65 |
Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari |
Refractory Monolithic Installation |
PLTU Banjarsari |
Oct 31 - Nov 23, 2018 |
2018 |
66 |
Refractory Installation Boiler 135 Mw unit 1 PLTU Banjarsari |
Refractory Monolithic Installation |
PLTU Banjarsari |
Feb 28 - March 28, 2019 |
2019 |
67 |
Refractory Installation Boiler 135 Mw unit 2 PLTU Banjarsari |
Refractory Monolithic Installation |
PLTU Banjarsari |
July 1-25, 2019 |
2019 |
68 |
Refractory Installation Boiler 2x16.5 Mw unit 2 |
Refractory Monolithic Installation |
PLTU Bolok |
April 28 - May 19, 2018 |
2018 |
69 |
Refractory Installation stack / chimney 2x50MW Bengkayang – Singkawang Kalbar PT Praba Conserium |
Refractory Monolithic Installation |
PT Praba Conserium |
May 29 – August 5, 2017 |
2017 |
70 |
Refractory Installation Boiler 3x35MW unit 3 – Jeranjang NTB PT PLN |
Refractory Monolithic Installation |
PT Praba Conserium |
May 29 – August 5, 2017 |
2017 |