Project Information

Refractory Monolithic/Brick on Stack/Chimney Installation 2x50MW at PLTU Parit Baru Site Bengkayang, Kec. Bengkayang, Tanjung Gundul, West Kalimantan

PT Praba Indopersada Consortium (Persero)

Kec. Bengkayang, Tanjung Gundul, Kalimantan Barat

Refractory Monolithic Installation

PLTU Parit Baru Site Bengkayang

Project Timeline

Refractory Monolithic Installation Project were carried out in in the following Periods:

Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
2013

Boiler 100 MW Unit 4
January 20th - 26th, 2013
December 1st, 2013 - January 4th, 2014

Boiler 100 MW Unit 3
March 10th - 17th, 2013







2017

Boiler 2x50MW
May 29th - August 5th, 2017