Project Information

Installation and maintenance of Refractory Monolithic Installation in Boiler 135 MW Unit 1 and Unit 2 at PLTU Banjarsari, Prabu Menang, East Merapi, Prabu Menang, Kec. Lahat, Lahat Regency, South Sumatra

PT.Bhimasena Power Indonesia

Lahat, South Sumatera

Refractory Monolithic Installation


PLTU Banjarsari

Project Timeline

Refractory Monolithic Installation Projects were is arried out periodically in the following periods:

Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia Brick lining indonesia, perusahaan brick lining, refractory indonesia, hafila daya utama, perusahaan refractory di indonesia, jasa refractory indonesia, proyek refractory indonesia
2016

Boiler 135 MW Unit 2
November 4th - December 31st, 2016











2017

Boiler 135 MW Unit 1
May 30th - June 26th, 2017











2018

Boiler 135 MW Unit 2
October 31st - November 23rd, 2018











2019

Boiler 135 MW Unit 1
February 28th - March 28th, 2019


Boiler 135 MW Unit 2
July 1st - 25th, 2019